Thursday, 2 November 2017

Statutory Remedies in Construction Disputes

Author: Graham Henderson
 
In the construction industry, insolvency is a regular occurrence that often leaves innocent companies unpaid for their goods and services. Insolvency also sometimes has a domino effect leading to the non-payment of multiple contractors and suppliers.
There are remedies available to companies to protect themselves from being affected by others’ insolvencies; however, those remedies typically have strict deadlines that cannot be missed. Companies often contact legal counsel after the deadlines have passed, missing opportunities to protect themselves.
The following chart provides a summary of the most prevalent statutory remedies available to companies involved in construction disputes:



 

Remedy

Companies Eligible for Remedy

Deadline

1.

Builders’ Lien

(Builders’ Lien Act, s. 6)

A company that provided materials or services for an improvement to land.

The company must register the lien within 45 days from the last day that materials or services were provided (90 days for improvements to oil or gas wells).

2.

Vendor’s Lien

(Builders’ Lien Act, s. 17)

A company that delivered materials for use in an improvement to  land, but whose materials have not yet been incorporated into the project.

The Vendor’s Lien expires as soon as the materials are incorporated into the improvement.

3.

Possessory Lien

(Possessory Liens Act, s. 2)

A company that expended money, labour or skill on a person’s movable property (e.g. objects and equipment, but not land), and in doing so enhanced the value of that property.

The Possessory Lien expires as soon as the property is no longer in the company’s possession.

4.

Unpaid Seller’s Lien

(Sale of Goods Act, s. 40)

A company that has sold goods but is still in possession of those goods.

The Unpaid Seller’s Lien expires as soon as the goods are no longer in the company’s possession.

5.

Public Works Claim

(Public Works Act, s. 14)

A company that provided materials or services for an Alberta government public works project.

For work on a roadway: The company must deliver a notice of claim between 30 to 90 days after the last day that materials or services were provided.

For any other work: The company must deliver a notice of claim within 45 days from the last day that materials or services were provided.

6.

Thirty Day Goods Claim

(Bankruptcy and Insolvency Act, s. 81.1)

A company that delivered goods to a purchaser that is now bankrupt. The goods must have been delivered within 30 days before the date of bankruptcy.

The company must deliver a written demand within 15 days from the date of the bankruptcy.

7.

Garage Keeper’s Lien

(Garage Keepers’ Lien Act, s. 2)

A company (known as the “Garage Keeper”) that stored or repaired a motor vehicle (including heavy-duty vehicles).

The Garage Keeper’s Lien expires as soon as the vehicle is returned to its owner, unless the Garage Keeper obtained a signed acknowledgment of indebtedness.

Further, in most cases, the Garage Keeper’s Lien must be registered within 21 days after the vehicle is returned to the owner (occasionally, earlier registration may be required).

There are many nuances to the statutory remedies and deadlines listed above. It is important for companies to be aware of the remedies and to contact legal counsel as soon as possible if they believe that one of the remedies may be applicable to their situation.
If you, or someone at your company, would like more information regarding your statutory remedies, feel free to contact any of the lawyers in our construction group.

Tuesday, 18 July 2017

Are Engineering Services Lienable?

Author: Corbin Devlin

Not every person who performs a service in relation to a construction project is entitled to a builders’ lien. Architecture and engineering services frequently give rise to questions about lien rights and holdback requirements. 

It Depends…

Architecture and engineering services give rise to a lien under the Alberta Builders’ Lien Act if those services relate to an “improvement” to land. So, a professional firm is entitled to register a lien for preparing construction drawings. But an architect or engineer providing services with respect to rezoning, subdivision and other development issues does not have lien rights; such services are considered to be not sufficiently connected to the process of construction. Several cases indicate that conceptual or schematic design work is also considered too far removed from the construction process to support a lien.

Some of the reported cases on this issue appear inconsistent, because the nature of engineering services varies project-to-project, and there is frequently some blending of services relating to development and services relating to construction.  The courts struggle sometimes to determine where to draw the line.

If a professional firm is entitled to a builders’ lien, the owner has a corresponding obligation to retain the statutory holdback in relation to the lienable scope of work.

Building Permits and Environmental Approvals

Master Robertson, Q.C. provides an excellent summary of the case law on this issue in J.K. Engineering Ltd v Red Quest Developments Ltd.

In that case, the landowner applied to court to strike out a lien registered by an engineering firm. In particular, the court considered work performed by J.K. Engineering to assist the landowner with obtaining approval of the storm drainage system from Alberta Environment. The necessary approval was not granted by Alberta Environment, giving rise to the payment dispute between the engineering firm and the landowner. The landowner argued that the lien was invalid because this environmental approval work was not directly related to the construction work. The Master compared this work with the work typically required for a builder to obtain a building permit, and concluded that the nature of such work is sufficiently connected to the process of construction to support a builders’ lien. The lien was valid. (However, it is important to note that construction of the development was well underway when J.K. Engineering’s approvals-related work was done. Also, J.K. Engineering was concurrently providing other design and construction services. It seems entirely possible the court would have come to a different conclusion if the environmental approval work stood alone.) This case illustrates the fine line that exists between a valid lien and an invalid lien.

Monday, 20 March 2017

Labour and Material Bond Claimants May Gain Further Rights

Author: Will Johnston


In Canada, the law imposes an obligation upon owners and general contractors named as “trustee” in a labour and material payment bond (“L&M bond”) to provide a copy of the L&M bond upon request by a potential claimant. The Supreme Court of Canada has granted leave to appeal where they will decide whether a trustee named in an L&M bond must proactively inform potential claimants of the existence of the L&M bond failing which they can be held liable to claimants who unwittingly lose their right to claim under the bond. The decision being appealed to the Supreme Court of Canada is from the Alberta Court of Appeal in Valard Construction Ltd v Bird Construction Company.

A conventional trust imposes onerous obligations upon trustees to act in the best interests of the trust beneficiaries. A typical L&M bond provided by a subcontractor to a general contractor includes language suggesting a trust:
"The Principal (subcontractor) and the Surety (bonding company), hereby jointly and severally agree with the Obligee (general contractor) as Trustee, that every Claimant (sub-subcontractor) who has not been paid … within 90 days … may sue on this Bond"
The Alberta Court of Appeal was divided as to whether an L&M bond creates a conventional trust and therefore divided as to the extent of the duties owed by a “trustee” under an L&M bond.

The Trial Judge and a majority in the Alberta Court of Appeal held that an L&M bond creates a limited trust. Therefore, a trustee named in an L&M bond does not have an obligation to proactively inform potential claimants of the bond’s existence. The majority was unwilling to impose the usual onerous obligations that exist in a conventional trust context upon an L&M bond trustee.

Justice Wakeling of the Alberta Court of Appeal wrote a lengthy dissent. In his opinion, the wording in a typical L&M bond creates a conventional trust thereby imposing the usual obligations on the trustee to advance the interests of the beneficiaries (i.e. potential bond claimants). He concluded that Bird Construction Company, as trustee, was liable to the sub-subcontractor, Valard Construction Ltd. for failing notify potential claimants of the bond’s existence by posting the L&M bond in a conspicuous place at the workplace.

Until the Supreme Court of Canada renders their decision, the law in Alberta does not require a general contractor to post a bond or to actively inform potential claimants that a bond exists. However a general contractor must disclose the existence of an L&M bond and provide a copy when requested by a potential claimant. We will report in a future blog post if the Supreme Court chooses to reverse the decision of the Court of Appeal.

Thursday, 9 February 2017

Fair Warning to Contractors – The Fair Trading Act’s Requirements Apply to Construction Contracts

Author: Sarah Levine

The recent Provincial Court of Alberta decision, R. v. 1587915 Alberta Inc. (“1587915”), is a stark reminder of the Alberta Fair Trading Act’s (the “FTA”) application to construction contracts, particularly for home renovations, and the potentially serious ramifications for contractors who deviate from the technical requirements of fair practice and compliance under the FTA. Not only can corporations be found guilty of contraventions of the FTA, but their directors can also be found guilty of the offence if they authorize the impugned conduct, whether or not the corporation has been prosecuted for the offence.

The Facts
 

1587915 involves 31 charges under the FTA and its Regulations against 1587915 Alberta Inc. and its directors, Kieron and Greta Warren. Kieron Warren (“Warren”) was also charged with four counts under the Criminal Code- two counts of fraud (under section 380(1)(b)) and two counts of theft (section 334(b)).

The 31 charges under the FTA and Regulations arose in respect of 6 families that 1587915 contracted with to provide home renovations. The charges against 1587915, Kieron and Greta Warren were as follows:

Six Counts   Section 104(1) FTA: No person may engage in a designated business unless the person holds a licence under this Act that authorizes the person to engage in that business;

Six Counts   Section 10(2)(a) of the Prepaid Contracting Business Licensing Regulation AR 185/99. A person who is engaged in a prepaid contracting business must ensure that every prepaid contract the person enters into complies with the requirements of section 35 of the Act;

Six Counts   Section 31(2) FTA: Within 15 days after a direct sales contract is cancelled, the supplier must refund to the consumer all money paid by the consumer and return to the consumer’s premises any trade-in or an amount equal to the trade-in allowance;

Six Counts   Section 6(4)(a) FTA: It is an unfair trade practice for a supplier to do or say anything that might reasonably deceive or mislead a customer.

Six Counts   Section 6(4)(n) FTA: It is an unfair trade practice for a supplier to represent that goods or services will be supplied within a stated period if the supplier knows or ought to know that they will not.

One Count   Section 10(3) Prepaid Contracting Business Licensing Regulation AR 185/99: A person who is engaged in the prepaid contracting business and who enters into a prepaid contract with a buyer must provide a copy of the signed contract to the buyer.

A prepaid contracting business is a business designated as such by the Designation of Trades and Businesses Regulation. These businesses include contracts for construction, maintenance or renovation where, critically, the prepaid contractor solicits, negotiates or concludes construction or maintenance contracts in person at any place other than their place of business and accepts money before all the work is done and/or the services are provided. Such operations require a license in order to engage in the prepaid contracting business. A direct sales contract is a consumer transaction where the consideration for the goods or services exceeds $25 and is negotiated or concluded in person at a place other than the supplier’s place of business or at a place other than a market place, auction, trade fair, agricultural fair or exhibition.

Behaviour in Breach of the FTA and Regulations
 

The six contracts from which the charges arose are variations on the same theme. In each of the contracts, references were made to completion deadlines and payment due dates. In each case, the families expressed concern that insufficient progress had been made by the dates when the contractor demanded more money. When the issue arose, as it did in each case, Warren referred back to the contract showing that the due dates of payments were clearly stated and were not related to progress.

In each of the six project situations, much the same pattern of conduct followed: after execution of the contract and the first payment, demolition began and generally proceeded. After demolition, customer complaints were made by all families regarding: lack of workers, lack of workers with appropriate skills, periods of inactivity and difficulty in reaching Warren. When meetings were held with Warren, he stated that the customers were late in making progress payments and in breach of the contract. Evidence was heard that additional contractors were called in by customers, and their explanation for engaging additional contractors was nonattendance by the contractor and lack of progress on their project.

Following a consideration of the evidence given by the parties, the Court found that 1587915, Kieron and Greta Warren were guilty of engaging in a prepaid contract without a license for all six contracts; 1587915 and Warren were guilty of failing to comply with the prepaid contract requirements; and that 1587915 and Warren were guilty of failing to refund money to their customers following the cancellation of a prepaid contract.

The Court did not find 1587915, Kieron or Greta Warren guilty of doing or saying anything to mislead a customer with respect to one of the contracts, but did find either 1587915 or Warren, or both, guilty of this charge with respect to the five other contracts. Similarly, 1587915, Kieron and Greta Warren were not found guilty of promising to supply goods with the knowledge that they would not be able to with respect to the first contract. However, 1587915 or Warren, or both, were found guilty of this charge with respect to the other five contracts. Lastly, the Court did not find Warren guilty of any of the four criminal charges of theft or fraud with respect to the home renovation contracts he entered into.

Tips and Takeaways
 

While Warren’s behaviour was particularly egregious, the moral of the story is to bear in mind the swath of technical requirements for licensing, entering into contracts, and otherwise engaging in certain business practices in accordance with the FTA and its Regulations.

The technical requirements of the FTA and its Regulations are not to be taken lightly when prepaid contractors and/or direct selling businesses contract with customers for construction services. The purpose of this legislation is ultimately to protect consumers from unfair business practices, ranging from misrepresentation and misleading customers to operating without proper licensing. As is evident from this case, the Courts will vigorously uphold this mandate in the interests of protecting the public, which can be to the detriment of contractors if they do not take care to comply with the FTA and its requirements.

Wednesday, 25 January 2017

Construction Holdback Requirements – Not for Dummies

Authors: Corbin Devlin and Kathleen Garbutt

Statutory construction holdback requirements can be remarkably tricky to interpret, presenting challenges for both novice and experienced players in the construction industry.

It is important to note that holdback requirements under the Alberta Builders’ Lien Act apply to projects of any size, from major industrial facilities to home renovations. In some sectors, particularly residential construction, holdback requirements are frequently misunderstood (to the considerable peril of the homeowner, who is often inexperienced regarding holdbacks and liens). In other sectors, particularly some professional design services and material suppliers, holdbacks are intentionally avoided, even if the Builders’ Lien Act is applicable.

On the other hand, there are all kinds of projects and lands exempt from builders’ liens – and therefore exempt from the corresponding holdback requirements. Most of the exemptions relate to projects of a “public” nature. Public highways and lands owned by irrigation districts are exempt. Interests in land owned by the federal or provincial governments are exempt. But not all infrastructure projects or projects with government involvement are exempt. For example, municipalities are not generally exempt - although particular municipal projects or lands may fall within another exemption.

Statutory holdback requirements are the responsibility of the owner, not the contractor or subcontractors or suppliers. However, statutory requirements are often supplemented by contractual holdback requirements. That is, contractors and subcontractors may also be responsible for holdbacks under their contracts and subcontracts, and sometimes construction managers are contractually responsible for taking care of statutory holdback requirements on behalf of construction owners. In Alberta, it is against the law to make a contract to the effect that the Builders’ Lien Act does not apply, but there is no problem with a contract that supplements the statutory requirements.

As a general rule, the statutory holdback requirement is 10% of the value of the work actually done. In practice, this typically means that the owner deducts 10% from invoiced amounts. In some provinces, the holdback has to be placed into a separate account, but in Alberta the owner simply keeps the holdback in pocket. After the work is complete, the owner must then wait 45 days before releasing the holdback, or 90 days if the work relates to an oil or gas well. The prudent construction owner (or lender) will always check the title to make sure no liens have been registered prior to releasing payment of the holdback. And if any liens have been registered, the prudent owner will make arrangements for discharge of those liens before making any further payments.

There are provisions for releasing the holdback early, or in stages (“progressively”) which can be very important on larger construction projects. In the simplest terms, a Certificate of Substantial Performance may be used to authorize the release of part of the holdback – that is, the holdback in relation to the value of work performed before the Certificate is posted – even though the work is not yet entirely complete. (The tricks and traps associated with the progressive release of holdbacks is a subject for a future article.)

Most importantly, why does the statute impose a holdback requirement? The underlying purpose is to provide a fund to protect subcontractors and suppliers in the event of insolvency or payment default by others involved in the project. In practical terms, the construction owner must abide by the holdback requirements, or face the risk of making double payment (i.e. coming up with the money to pay subcontractors and suppliers out of the owner’s own pocket if there is no holdback).

Holdbacks are a big consideration for construction owners and builders alike in terms of construction financing, cash flow, payment security, and just plain old contract administration. Contact us if you require more information regarding your holdback rights and obligations.

Tuesday, 3 January 2017

Lien Pitfall – Transfers of Land

Author: Corbin Devlin

When a transfer of title takes place, it is possible that builders’ lien claimants automatically lose their builders’ lien rights. This is another Builders’ Lien Act trap for the unwary.

If a lien is registered before the transfer of land, it will survive the transfer. (Or more likely, the transfer will be delayed until the lien is discharged.) However, if the transfer of land occurs after lien rights arise, but before the contractor or supplier registers a lien, then lien rights are at risk. That is because only a statutory “owner” is subject to lien claims. If the purchaser did not request the work to be performed or materials to be supplied and was not otherwise an active participant in the construction project, then the purchaser is not an “owner” within the statutory definition.

Example 1 – Residential Construction
 

By way of an example, a residential home purchaser had an agreement with the developer that he would construct and deliver the home to them. The developer owned the land in question and contracted to have the home built. When the home was completed, title was immediately transferred to the purchaser. The builder did not get paid by the developer and registered a builders’ lien. Notwithstanding the fact that the lien was registered in time, the court declared the lien to be invalid. The purchaser was not an “owner” (as that term is defined in the Act). The builder still had a right to sue the developer for payment, but the builder had no lien rights.

The Test – Statutory Definition of “Owner”
 
In the Builders’ Lien Act, the following definition applies:


…“owner” means a person having an estate or interest in land at whose request, express or implied, and
  1. on whose credit,
  2. on whose behalf,
  3. with whose privity and consent, or
  4. for whose direct benefit,
work is done on or material is furnished for an improvement to the land and includes all person claiming under him whose rights are acquired after the commencement of the work or the furnishing of the material…
This definition, like much of the Builders’ Lien Act, is badly in need of translation into simple English.

Whether or not someone with an interest in land meets this antiquated statutory definition of “owner” will almost always fall to be determined on the question whether they expressly or impliedly requested the work. That is, were they active participants in the construction project? In the example above, the purchaser simply contracted to buy a completed house, and there was no evidence that (for example) they directed any changes during construction, so the court concluded that they were not sufficiently involved in the construction project to meet the statutory definition; simply speaking, they did not request the work.

Example 2 – Commercial Construction
 

This issue seems to come up most often in new home construction, but it can occur on any construction project. In our second example, a commercial contractor registered its lien on time, but not before the land had been transferred to a purchaser. The purchaser approved the specifications for the building, made requests (through the vendor) for changes during construction, and had a representative on the construction site from time to time. But the court held this was still insufficient to meet the statutory definition of “owner.” Where the party with an interest in the land (i.e. the purchaser) is not a party to the construction contract(s), it must be shown that they otherwise “actively participated” in the construction process so as to meet the statutory definition of “owner.”

Practical Tip
 

The practical consequence is that contractors, subcontractors and suppliers must be aware of any situation where the interest in land they are working on is likely to be sold or otherwise transferred. If a developer transfers title during construction or immediately after completion – to a purchaser who isn’t actively involved in the construction process - unregistered builders’ lien rights are lost. In appropriate circumstances, this might mean that it is desirable to register a lien before the transfer takes place, in which case the lien survives the transfer. Since this will usually have the effect of holding up the transfer completely, this should be done only after giving due consideration to the consequences. In other circumstances, this might mean it is prudent to seek other forms of security for payment at the outset