Lien Rights –When the Developer Doesn’t Have an Interest
in the Land
In an earlier article, we warned of the risk of loss of lien
rights if a transfer of land occurs during construction. A 2018 court decision
reminds us that there is also a risk of loss of lien rights if the party
contracting the work doesn’t have a legal interest (ownership) in the land,
such as when (for example) an expected transfer of land doesn’t go
through.
The Recent Example
In Georgetown Townhouse GP Ltd v Crystal Waters
Plumbing Company Inc, 2018
ABQB 617, the developer/owner Georgetown agreed to sell 48 lots to
ReidBuilt Homes. The contract between Georgetown and Reidbuilt allowed
ReidBuilt to occupy the lands and begin construction. However, the lands
would be transferred by Georgetown only upon sale of the lots to individual
homebuyers.
When ReidBuilt came into financial problems, many trades
registered liens against the lots in question. The problem is, the trades
were working for ReidBuilt but the lands were owned by Georgetown. On a
court application to determine if the liens (against the lands owned by
Georgetown) were valid, Master Prowse determined that Georgetown was not
“sufficiently involved” in the construction process to make Georgetown an
“owner” as defined in the Builders’ Lien Act (BLA). The liens were all
invalid.
That Quirky Legislation
This issue arises
in large part because the BLA has a unique definition of “owner,” and it is
only the interest of an “owner” as defined that is subject to claims of
lien. Section
1(j) of the BLA
defines an owner as follows:
“owner” means a person having an estate or interest in land at whose
request, express or implied, and
(i) on whose credit,
(ii) on whose behalf,
(iii) with whose privity and consent, or
(iv) for whose direct benefit,
work is done on or material is furnished for an improvement to the land and
includes all persons claiming under the owner whose rights are acquired after
the commencement of the work or the furnishing of the material.
There is now a substantial body of case law around the
question what it means to expressly or impliedly request the work.
Mere knowledge by the registered owner that the work is being done is not
sufficient. Rather, the courts have decided the registered owner must be actively
involved in the building process for lien rights to exist.
What is Sufficient Involvement to Trigger Lien Rights?
In the Georgetown case, the lien claimants argued that the
registered owner Georgetown expressly or impliedly requested the work based on
the following facts:
- Georgetown had
the right to approve the style and colours of the homes to be constructed.
- ReidBuilt was
required to obtain Georgetown’s approval for the plans for the house before
applying for a building permit.
- ReidBuilt was
to provide utility servicing within the lot boundaries but only with
contractors approved by Georgetown, and the work was to be supervised by
Georgetown’s engineers.
- ReidBuilt was
required to keep the lots with an orderly and tidy appearance to the
satisfaction of Georgetown.
- Georgetown was
to provide marketing support to ReidBuilt for the sale of homes on the lots.
- Georgetown’s
approval was required for ReidBuilt’s onsite signage and advertising.
However, despite
all of these obligations, there was no evidence that Georgetown in fact gave
any of the approvals, or participated in any of the ways contemplated in the
agreement between Georgetown and ReidBuilt, aside from Georgetown setting up
and maintaining a website that referred to ReidBuilt as the builder for the
subdivision. The court concluded that Georgetown’s contractual
authority over the development is a relevant factor to consider, but not
as significant as what in fact happened. With no evidence of Georgetown’s
active involvement in the building process, the liens were invalid.
Not An Isolated Case
Similar situations have led to similar conclusions by the
court in the past.
In Stealth
Enterprises Ltd. v Hoffman Dorchik, 2000
ABQB 311 (CanLII), S & U Homes Ltd. was the registered owner of an
apartment building. They made an agreement to sell the building to the
developer (632766 Alberta Ltd.) who intended to convert it into condominiums.
632766 refinished four of the apartment suites into show suites and spent other
money on refreshing the lobby, before the land transfer was completed. The deal
collapsed and an unpaid contractor (hired by 632766) registered a lien against
S&U’s title. The only evidence of active participation by S &U
related to some directions regarding cleaning the apartments for rental.
The court determined the lien was not valid.
In E. Gruben’s
Transport Ltd. v Alberta Surplus Sales Ltd., 2010
ABQB 244 (CanLII), the landowner Alberta Surplus Sales agreed to sell 150
acres of land to 1327923 Alberta Ltd. Alberta Surplus allowed 1327923 to
move ahead with development (road construction) prior to closing the
deal. The roadbuilding subcontractor (E. Gruben’s Transport) liened the
lands when the deal fell through (and consequently Gruben’s didn’t get
paid). The court determined that Alberta Surplus Sales “had no direct or
indirect involvement in arranging for the road work to be done;” so the lien
was not valid.
Finally, in Acera
Developments Inc. v Sterling Homes Ltd., 2010
ABCA 198 (CanLII), the issue went to the Alberta Court of Appeal. Acera
was the developer/landowner who agreed to sell the land to Sterling and allowed
Sterling to build on the land prior to completion of the purchase and
subdivision of the land. When subdivision approval of the land was
refused, and Sterling did not get paid, Sterling registered a builders’ lien.
Acera's architectural and construction guidelines required that Acera approve
the construction plans, elevations, finished grades, finishing materials and
colours, final grade slips, setbacks, foundation designs, auxiliary buildings
and fencing, and landscaping. All such plans were in fact approved prior to
construction. Further, the construction was inspected by Acera as work
progressed. In these circumstances, the court sided with the lien
claimant – the lien was valid because there was sufficient evidence of Acera’s
active involvement in the work.
Three Categories of Similar Cases
As Master Prowse states in the Georgetown case: “There are
three common categories of cases where this issue arises:
(i) a landlord
(registered owner of land) disavows liens placed on its land by unpaid
contractors of a tenant,
(ii) a purchaser
who agrees to buy land upon which a building is to be built, and later takes a
transfer of the land after the structure has been built, disavows liens
subsequently placed on his/her land by unpaid contractors of the builder,
(iii) a developer/vendor
(registered owner of land) who agrees to sell land, and allows the purchaser to
build on the land prior to completion of the sale, disavows liens placed on its
land by unpaid contractors of the purchaser.”
The present article deals with category (iii – contracting
with purchaser of lands before completion of the sale of the lands). We
have addressed the other two categories in prior articles: (i – landlord
and tenant) and (ii – vendor
and purchaser).
Room For Mischief
Contractors should be very attentive to these risks.
Most of the time, these situations arise innocently enough when a developer
becomes insolvent. But we have also seen developers deliberately arrange
their affairs to protect the project from claims of lien (i.e. isolating the
registered owner of the lands from any active involvement in the work).
In either case, contractors should be alert to situations where their statutory
lien rights may be compromised.
In the present context, this means making some investigation
if the party who is contracting the work has a legal interest in the
lands. If the party contracting the work has no legal interest in the
lands, further inquiry is required to determine if the party who actually owns
the lands is actively participating in (requesting) the work. Keep in
mind, the registered owner’s right to actively participate in the work is not
sufficient; there must be active participation by the registered owner in
fact. If these inquiries suggest that lien rights may not exist, the
prudent contractor will mitigate risk in some other fashion, such as requiring
other security for payment from the party contracting the work.
No comments:
Post a Comment