A recent
decision of the Alberta Court of Appeal serves as a stark reminder that the
Consultant appointed in a CCDC contract wields considerable authority to
determine the rights of the parties.
In ASC(AB) Facility Inc v Man-Shield (Alta) Construction, 2019 ABCA 379, the Court considered a dispute regarding the amounts owing for work performed
pursuant to a CCDC2 fixed price contract. The Consultant determined that
the Contractor did not perform some of its work to contractual requirements and
that the Owner could deduct the value of that work from amounts otherwise owing
to the Contractor. The Contractor sued for the contract value, asking the
Court to find that Consultant erred in deducting various deficiency costs when
certifying the final payment due to the Contractor.
In the
summary trial decision in 2018, Justice Antonio stated: “…CCDC2 makes it clear
that the Consultant was empowered to make decisions, in real time or as close
to it as possible, in order to keep the project moving. The Consultant had access
to the work site and the expertise to evaluate the work he saw. He was
regularly involved with the parties, the work, the contract, and the parties’
interactions under the contract. He has expertise in relevant areas. The
parties chose this person, equipped with these advantages, to make decisions
about the state of completion of the work and any resulting contractual
obligations. This Court lacks those advantages. Therefore, as a matter of
contractual interpretation, precedent, academic rationale, and practicality,
this Court will defer to the Consultant’s determinations on questions of fact,
unless they reveal significant errors. The same will apply to the
Consultant’s interpretation of the contract…”
The
Contractor appealed this summary trial decision. The appeal decision was
issued in October 2019. The Court of Appeal agreed with the summary trial
judge, ruling that deference to the Consultant’s decisions is appropriate
“absent demonstrable and significant error or compelling evidence to the contrary.”
In the result, there was insufficient evidence for the Court to determine the value of various alleged deficiencies (this was only a summary trial, without live witnesses). So, the Court directed a full trial of certain issues. But the Contractor lost the argument that the Court should disregard the Consultant’s valuation of deficiencies.
In the result, there was insufficient evidence for the Court to determine the value of various alleged deficiencies (this was only a summary trial, without live witnesses). So, the Court directed a full trial of certain issues. But the Contractor lost the argument that the Court should disregard the Consultant’s valuation of deficiencies.
Practical Implications
Considering
these comments, it is imperative to ensure at the outset that the Consultant
appointed in a CCDC contract is appropriate to fulfill the important role of
neutral decision-maker under the contract.
It is often
a fallacy that “the parties” choose the Consultant; although the contract is
(in theory) a negotiated agreement, in many cases the Contractor has no input
on the designation of the Consultant by the Owner. Sometimes, this is due
to inequality of bargaining power; other times, this is due to the Contractor
(actually, both parties) paying insufficient attention to this important
element of the contract.
Pursuant to
the CCDC contracts, the Owner pays the Consultant. In most cases,
Consultants are professionals with reputational concerns, and they properly
fulfill their role as neutral decision-maker, regardless of who pays them.
But we have also seen cases in which the Consultant shows significant bias
in favour of the party who is paying their fee accounts.
We have
also seen circumstances in which the project Consultant is lacking necessary
experience or qualifications to properly fulfill the role. Remarkably, we
have also seen several cases in which the Consultant is named in the contract, but not actually engaged and paid by the Owner to properly fulfill the
role. Such unfortunate circumstances often lead to a departure from the
contractual payment certification process, leaving the parties in unpredictable
territory when a payment dispute arises.
Such
circumstances tend to present a greater risk to the Contractor than the
Owner. But it is a risk to both parties that legal disputes are more
likely to ensue if the project Consultant is not suitable or properly supported
to perform the role.
The ASC
case serves as a reminder to take due care in the selection of the Consultant -
and to heed the decisions and interpretations made by the Consultant during the
course of the project.
No comments:
Post a Comment