A recent Alberta
Court of Queen’s Bench decision provides an example where services may be
performed on one site yet give rise to lien rights on another site. Northern
Dynasty Ventures Inc v Japan Canada Oil Sands Limited considers the
validity of builder’s lien claims brought by a lessor of equipment. The
decision arises from an appeal of a Master’s Order declaring the lien of a
lessor of equipment valid.
By way of
background, the Defendant is the operator of an oil sands project near Fort
McMurray, Alberta (the “Project”) and entered into a Master Agreement
with Highway Rock Products Ltd. (the “Contractor”). In turn, Northern
Dynasty Ventures Inc (“NDV”) and Tyalta Industries Inc. (“Tyalta”)
were subcontractors to the Contractor. NDV entered into an agreement with the
Contractor granting the Contractor an exclusive license to remove sand and
gravel from a gravel pit located approximately 30 kilometers away from the
Project site (the “Gravel Pit”), accessible by road at a driving distance of 89
kilometers. Tyalta rented to the Contractor equipment used to crush and screen
sand and gravel at the Gravel Pit. All of the gravel was provided to the
Defendant for its use in connection with the Project.
Tyalta registered a
lien against the Project site. The Defendant sought to have the lien discharged
on the basis that it was invalid, particularly because the Project was not the
location – or even near the location – where the rental equipment was used. Determining
the validity of Tyalta’s lien required the Court to interpret section 6(4) of
the Builders' Lien Act (the “Act”), which provides:
6(4) For the purposes of this Act, a person who rents equipment to an owner, contractor or subcontractor is, while the equipment is on the contract site or in the immediate vicinity of the contract site, deemed to have performed a service and has a lien for reasonable and just rental of the equipment while it is used or is reasonably required to be available for the purpose of the work.
In coming to its
decision, the Court answers three questions: (1) where is the contract site;
(2) what is the meaning of immediate vicinity; and (3) is there a common
purpose between the sites.
Ultimately, the
Court found that the Project was the “contract site.” However, after
considering the context of the matter, the Court determined that
notwithstanding the distance, the Gravel Pit was within the “immediate vicinity”
of the contract site, stating:
I find on the facts of this specific case that the gravel pit and the [Project] site are in the immediate vicinity of each other. Thus, as the rental equipment was at all relevant times located at the gravel pit, the rental equipment was in the immediate vicinity of the contract site... The gravel was not obtained out of country, out of province, or even in central or southern Alberta. Given the nature of gravel pits, immediate vicinity must be considered in context.
When assessing the
purpose of the work, the Court found that the work performed at the Gravel Pit using
Tyalta’ rental equipment resulted in gravel that was required for the Project.
This gravel was not available at the Project and had to be transported from the
Gravel Pit. Thus, the Court determined that the two sites clearly had a common
purpose, the construction of the Project, and the work performed at the Gravel
Pit was an integral part of the overall Project.
In summary, though
equipment may not be used at a contract site, a lessor of equipment may have a
valid lien against the contract site so long as their equipment was integral to
the contract site and used somewhere within the immediate vicinity, which
depending on the context may even be a 89 kilometre drive away.
Read the full
decision here.
I'm really enjoying the design and layout of your site. It's a very easy on the eyes which makes it much more enjoyable for me to come here and visit more often. Did you hire out a designer to create your theme? Superb work! Alexandr Shcolyar
ReplyDelete